High-Voltage Bus Line Installation

Project Overview

The electrical team just completed a brand new bus line installation project in Upstate, SC. Prior to this, we tied in the existing bus lines, and our abilities to understand and align the right team led to the new electrical project. We began with prework by installation of conduit racks, two 4″ conduit parallel runs symmetrical to the existing conduit route. JDI then installed two 10 foot sections of 800 AMP bus duct; we were then able to pull an 800 AMP feeder to feed the new bus ducts through the 4″ conduits.

Results

JDI ran 350 feet of conduit to feed the new bus duct, which was part of a planned shutdown with the client to achieve the results they wanted. The new bus will feed six machines for the client’s increased production needs.